Link: GAO Decision Protestor: American Material Handling, Inc. Agency: General Services Administration Disposition: Protest Denied. _____________________________________________________________________________________________________ GAO Digest: Agency properly terminated the protester’s contract for a mobile crane for the Department of the Air Force and reopened the competition for the crane, where the solicitation omitted a mandatory Defense Federal Acquisition Regulation Supplement clause requiring
The post American Material Handling, Inc., B-406739, August 14, 2012 appeared first on Bid Protest Weekly.